Given a list of activities for a small project as shown in the following table:
Activity Duration (days) Early Start Early Finish Late Start Late Finish Total Float Free Float
A 0 5 0
B 5 11 0
C 11 13 6
D 0 4 1
E 4 7 4
F 11 19 0
G 19 20 0

It is required to:
• Complete the missing data in the table; and
• Draw The Activity-On-Node network, assuming that any relationship you need is FS=0.

Sample Solution