Question 1: (4 Marks)
• Draw the following network using Precedence Diagram Method and determine the critical path(s); PDMin; Total Float for each activity considering the following data:
Activity Depends on Duration (days)
A -- 6
B -- 5
C -- 6
D A 5
E A,B 8
F B 3
G E 6
H G 8
I F 9
J C,E 7
K J,H 6
Sample Solution